Torrevieja port promenade works delayed again, now set to finish 21 November
Why it matters: The lower area and the ramp to the shopping centre have been partly closed for weeks; full pedestrian access will be possible once the paving in front of the Aduana is finished, with completion now planned for 21 November.
Details:
- The reurbanisation project covers the old Aduana area and a new promenade along the bay.
- The contract was awarded to González Soto for €5,055,519 (including VAT) on 31 October 2025.
- The original execution period was set at 15.5 weeks after a six-week reduction offered by the contractor.
- There have now been four deadline extensions, with the latest moving completion to 21 November.
- Pending works focus on paving in front of the old Aduana building and finishing a steel bench structure, still awaiting its wooden seat.
- A new children's play area will open to the public once the works are officially received.
What it means for you: The lower area and the ramp to the shopping centre have been partly closed for weeks; finishing the paving will allow full pedestrian access. The new children's play area will only open after the final acceptance of the works.
The source article appears to be truncated.
Fourth extension for Torrevieja port promenade works
The reurbanisation of the area around the old Aduana building and the creation of a new promenade along the bay in Torrevieja have been delayed for a fourth time. The new expected completion date is now 21 November. The project, awarded to González Soto for €5,055,519 (including VAT) on 31 October 2025, originally had a tender period of five months, but the contractor offered a six-week reduction, setting the execution period at 15.5 weeks. Since then, the deadline has been extended four times, with three changes made earlier in 2026 and the latest moving completion to 21 November.
What is included in the project?
The works cover the renewal of the old fishing quay frontage, the promenade along the cantil, and the urbanisation of the area around Muelle Mínguez, the old Aduana, and the new leisure centre. Improvements include new paving, service networks, public lighting, urban furniture, and better accessibility and pedestrian connections across the port front. Remaining tasks focus on completing paving in front of the Aduana building, which houses administrative offices, and finishing a bench with a steel structure, still awaiting its wooden seat, separating the leisure area from the promenade. Workers are also working on Saturdays and Sundays.
Access and future openings
Completing the paving in front of the Aduana will allow these areas to open fully to pedestrians; they have been partly closed for weeks. Once the project is officially received, a large new children's play area built as part of the scheme will open to the public.
Other port projects
This contract is separate from two other major works in the port: primary and secondary electrification and the new multi-use esplanade. The primary electrification, awarded to UTE Orthem-Abala for €3,265,085, provides the main electrical infrastructure for the fairground and leisure centre. The secondary electrification, awarded to Abala Infraestructuras and Orthem Servicios y Actuaciones Ambientales for €7,863,401.06, completes the internal distribution and includes paving, urban furniture, equipment, and landscaping for the new esplanade. The esplanade works have also been extended to the second week of November, with remaining work focused on finishing the central axis of the former Avenida de la Libertad. The lane nearest the pavement, the "acera del Bahía", will not be urbanised in this work, will stay as it is for now and is not expected to open to traffic.