Torrevieja awards €1,250,900 contract for first 40 port craft market stalls
Why it matters: The Ayuntamiento has awarded a contract to build 40 new craft market stalls at the port, starting the return of vendors to the seafront. The new stalls will be installed after urbanisation works are finished.
Details:
- Contract awarded to Construcciones y Movimientos OVISA, S.L. and Mistral 3000, S.L. for €1,250,900.86 (VAT included).
- Covers construction and assembly of the first 40 stalls for the future craft market at the Puerto de Torrevieja.
- Award price is 4.74% below the tender budget of €1,313,143.88, saving €62,243.02.
- Contract duration is five months from signing, with no extension possible.
- Warranty on installations will be 48 months (36 months above the minimum required).
- Stalls will be installed in the Aduana del Puerto area and Paseo de la Libertad after urbanisation works are completed.
What it means for you: The first 40 new craft market stalls will be installed at the port after urbanisation works are finished. The contract lasts five months from signing, with no extension.
The Junta de Gobierno Local (local government board) of the Ayuntamiento (town hall) of Torrevieja has awarded the construction and assembly of the new stalls for the craft market to the companies Construcciones y Movimientos OVISA, S.L. and Mistral 3000, S.L., who jointly submitted a bid, for an amount of €1,250,900.86 (VAT included).
The project covers the first 40 stalls of the future craft market at the Puerto de Torrevieja and will allow for the gradual return of vendors to the city’s seafront. The award price is broken down into €1,033,802.36 as the taxable base and €217,098.50 corresponding to 21% VAT. The offer includes a 4.74% reduction compared to the tender budget, set at €1,313,143.88 (VAT included), which represents a saving of €62,243.02.
The contract will last five months, starting after its formalisation and the signing of the commencement act, with no possibility of extension. In addition, the awarded companies have offered to extend the warranty by 36 months over the minimum required year, so the installations will have a total warranty period of 48 months.
The new stalls will provide the market with modern and uniform facilities, integrated into the redeveloped port area. The tender documents require that all wood used, including cross-laminated timber (CLT) and, where applicable, auxiliary wood, must have FSC certification or equivalent, with PEFC or other recognised equivalent certifications accepted, as well as documentary control to guarantee traceability.
Installation is planned for the Aduana del Puerto area and on Paseo de la Libertad, once the urbanisation works for these spaces are completed and accepted. The tender planning foresees the progressive delivery and installation of the stalls as their manufacture progresses. This first phase includes 40 units, with the possibility in the tender to extend the contract up to a maximum of 48. The project is part of the overall plan for the craft market, which initially foresees the progressive introduction of up to 166 stalls, according to the demand from artisans and compliance with the requirements established for the activity.
Three bids were submitted for the procedure. The final evaluation of the bidding companies was as follows:
- Construcciones y Movimientos OVISA, S.L., Mistral 3000, S.L. (joint offer)
- Creaciones Parma, S.L.
- No score: excluded
The joint offer from OVISA and Mistral 3000 obtained the highest total score, with 96.32 out of 100 points: 81.32 for the financial offer and the 15 points available for the extended warranty. GRUEXMA achieved 85 points for its financial proposal, with no additional points for warranty extension. Creaciones Parma was excluded from the procedure after the documentation correction phase required in the tender documents, so it was not scored.
With this award, the Ayuntamiento de Torrevieja continues the recovery of the craft market as part of the transformation of the port front, with facilities that will help strengthen the commercial and tourist offer of this new space for residents and visitors.
Source: Ayuntamiento de Torrevieja ↗ · Discuss on Telegram ↗