Torrevieja begins repairs to indoor pool after May air duct collapse

Photo: Informacion.ES

Why it matters: Repairs to the collapsed air duct at the Palacio de los Deportes indoor pool are expected to take three months, plus several weeks to formalise the contract, with completion expected by mid-December.

Details:

  • The Ayuntamiento (town hall) signed a contract with Proyectos e Instalaciones Térmicas to replace the air duct at the Palacio de los Deportes indoor pool.
  • The contract is worth €107,000 (including VAT), plus €14,000 for project design.
  • Three companies submitted bids; the chosen offer was €27,000 below the starting price.
  • Repairs will also improve ventilation in the boiler room.
  • The old metal duct was badly corroded by moisture and chemicals; the new duct will be textile and placed outside the water zone.
  • The works will last three months, plus several weeks for formalising the contract; completion is expected by mid-December.

What it means for you: The repairs are expected to be completed by mid-December.

Based on the @torreUA summary; original source not available.

Repairs underway at Palacio de los Deportes indoor pool

The Ayuntamiento (town hall) of Torrevieja has begun works to reopen the indoor pool at Palacio de los Deportes after the air duct collapsed on 14 May during a public opening. The contract was signed with Proyectos e Instalaciones Térmicas for €107,000 (including VAT), plus €14,000 for project design. Three companies submitted bids, and the selected offer was €27,000 below the starting price, according to Informacion.ES.

What the repairs involve

The project includes replacing the old metal air duct, which was found to be badly corroded by moisture and chemicals. The new duct will be textile and installed outside the water area to make maintenance easier, and the previous design will not be repeated. Ventilation in the boiler room will also be improved.

Timeline and incident background

The works are expected to last three months, plus several weeks for contract formalities, with completion expected by mid-December. The incident in May followed an earlier problem with the fixings: an anomaly was found in April, the pool was temporarily closed, and Serveo carried out repairs. After the collapse, the Ayuntamiento requested a report on the works and the cause of the failure.