Torrevieja desalination plant expansion now expected to finish on 18 May 2027
Why it matters: The expansion of the Torrevieja desalination plant is now expected to be finished on 18 May 2027, delaying increased water supply for agriculture and urban use in the Vega Baja and nearby cities.
Details:
- Acuamed, the state company, approved a new delay on 24 September, setting the expected completion for 18 May 2027.
- The project aims to increase capacity from 80 to 120 hectometres of water per year.
- The works began in July 2024 and were initially due to finish in February 2026.
- The main contract value has risen from €89.49 million to €97.6 million, a 9.12% increase after five modifications.
- Final water delivery to users is not expected before the second half of 2027 due to required testing.
- A separate project for connecting some agricultural users, such as Riegos de Levante Margen Izquierda, remains pending.
What it means for you: Users will not be able to use the new water volumes before the second half of 2027 at best, since commissioning will also involve testing. The expansion works are now scheduled to last 33 months and 24 days instead of the original 20 months.
The source article appears to be truncated.
The expansion of the Torrevieja desalination plant has been delayed again, with the new expected completion date set for 18 May 2027. According to Informacion.ES, the board of Acuamed, the state company responsible for the project, approved this extension on 24 September in an agreement that has only now become known. This is the second delay for the works, which are intended to increase the plant's capacity from 80 to 120 hectometres of water per year.
The project began in July 2024 and was originally due to finish in February 2026. The total duration of the works is now set at 33 months and 24 days, more than a year longer than planned. The main contract, awarded to a consortium of Ferrovial, Cadagua and Sacyr, has seen its budget rise from €89.49 million to €97.6 million, a 9.12% increase after five modifications.
The expansion involves reinforcing pre-treatment and reverse osmosis phases, installing two new seawater pumps at the Poniente dock near Playa de Los Náufragos, and building a 4,000-square-metre facility for new equipment. The plant will need to draw about 267 hectometres of seawater annually to produce the planned 120 hectometres of fresh water, returning the remainder as brine to the Mediterranean through the existing submarine outfall, which will go from 43 to 64 active diffusers.
Despite progress on some construction elements, the new water volumes will not be available to end users, including agricultural communities reliant on the Tajo-Segura transfer and the Mancomunidad de Canales del Taibilla (which supplies 27 Vega Baja municipalities, Elche, Alicante, San Vicente del Raspeig, Crevillent, Santa Pola and Aspe), until at least the second half of 2027, as commissioning will require further testing. Some agricultural users, such as Riegos de Levante Margen Izquierda, still lack direct connections, which depend on a separate infrastructure project that remains at the planning stage.
Acuamed is studying a solar plant announced by the Government in February 2024, still at pre-project stage. The latest proposal spoke of using land now in production in Los Montesinos, Almoradí, San Miguel de Salinas (where the largest areas would be) and Orihuela. The plant would require about 100 hectares of land for the planned energy output.