Torrevieja desalination plant faces €1.58 million pipeline cleaning and expansion delay

Photo: TorreviejActual

Why it matters: Marine deposits have reduced the hydraulic capacity of the intake pipeline at the Torrevieja desalination plant by about 17%. The plant’s expansion, originally due in February 2026, is now planned for completion on 18 May 2027.

Details:

  • Hydraulic capacity of the intake pipeline has dropped by about 17% due to mussels, sand and other marine deposits.
  • 900 metres of the 2,280-metre pipeline must be cleaned, with 63 tonnes of deposits to be removed.
  • The additional technical work, including cleaning, access points and pump modernisation, is estimated to cost approximately €1.58 million.
  • The plant’s expansion aims to raise annual output from 80 to 120 million cubic metres of water.
  • The main contract for the expansion is reported to stand at about €97.6 million after five modifications.
  • The new planned completion date for the expansion is 18 May 2027, instead of February 2026.

What it means for you: The construction work is now planned for completion on 18 May 2027. The work to clean the pipeline and modernise equipment is estimated to cost about €1.58 million. Testing and commissioning will be needed after construction before extra water reaches consumers.

Mussels, sand and other marine deposits have built up inside the main intake pipeline at the Torrevieja desalination plant, reducing its hydraulic capacity by about 17%. To address this, 900 metres of the 2,280-metre pipeline will be cleaned and around 63 tonnes of deposits removed. In some sections, the layer of mussels, sand and organic matter is more than ten centimetres thick. The deposits not only reduce space but also make the inner surface rougher, increasing resistance and putting extra strain on the pumps. Hydraulic tests in April 2025 found flow resistance more than three and a half times higher than expected.

The planned technical work includes cleaning the pipeline, installing eight new technical access points for maintenance and ventilation, and modernising the pumps. The direct budget for this additional work is approximately €1.58 million.

This problem has arisen during a major expansion project at the plant, which aims to increase annual production from 80 million to 120 million cubic metres of water, a 50% increase. The plant is a strategic facility for the region, with desalinated water entering the supply system of the Mancomunidad de los Canales del Taibilla and being used for agricultural irrigation connected to the Tajo-Segura system.

The expansion was originally scheduled for completion in February 2026, but the new planned completion date for the construction work is 18 May 2027. After five modifications, the main contract is reported to stand at about €97.6 million. Once construction ends, testing and commissioning will still be required before the extra water reaches consumers. As TorreviejActual notes, the reliability of the intake system and ongoing maintenance are essential for the plant to deliver the expected increase in water supply.