Torrevieja proposes €16.7 million contract to ABALA for Museo del Mar y de la Sal works

Photo: Ayuntamiento de Torrevieja

Why it matters: The Ayuntamiento plans to award a major contract for the Museo del Mar y de la Sal and surrounding regeneration, but the award is not final yet.

Details:

  • The Mesa de Contratación (tender committee) proposes awarding the works to ABALA Infraestructuras, S.L.
  • ABALA's offer is €16,669,412 (VAT included), 7.95% below the starting budget of €18,109,085.
  • Five companies submitted bids; ABALA scored highest with 96.9781 points out of 100.
  • The maximum execution period is 20 months from the signing of the act verifying the start of works (acta de comprobación del replanteo); works on the Casa de la Administración de las Salinas and the Caballete must be completed within 12 months.
  • ABALA offers to extend the guarantee by 45 months, for a total of 57 months (four years and nine months).
  • The project includes the museum, its surroundings, and rehabilitation of the Casa de la Administración de las Salinas and the Caballete.

What it means for you: The proposal has gone to the contracting authority, which will continue the steps before awarding; it is planned to ask ABALA for the documentation and a definitive guarantee.

The Mesa de Contratación (tender committee) of the Ayuntamiento de Torrevieja, meeting on 2 October, unanimously agreed to propose ABALA Infraestructuras, S.L. as the contractor for the works on the Museo del Mar y de la Sal and the regeneration of its surroundings, along with the rehabilitation of the Casa de la Administración de las Salinas and the Caballete. The company received the highest score in the process, with 96.9781 points out of 100.

ABALA's offer amounts to €16,669,412, VAT included, compared to a base tender budget of €18,109,085. This proposal represents a reduction of 7.95% and a decrease of €1,439,672 from the starting amount. The offered price is broken down into €13,776,374 as the base and €2,893,038 for VAT.

Five companies submitted bids

In the open procedure, subject to harmonised regulation and ordinary processing, five companies submitted bids. The classification approved by the Mesa, ordered from highest to lowest score, is as follows:

  • ABALA Infraestructuras, S.L.
  • COBRA Instalaciones y Servicios, S.A.U.
  • EIFFAGE Infraestructuras, S.A.U.
  • LLOP Proyectos Integrales, S.L.
  • CITANIAS Obras y Servicios, S.L.U.

Maximum execution period of 20 months

The total maximum duration of the works contract will be 20 months from the signing of the act verifying the start of works (acta de comprobación del replanteo). The execution is organised into two concurrent phases: the works to regenerate the Museo del Mar and its surroundings have a maximum period of 20 months, while the actions on the Casa de la Administración de las Salinas and the Caballete must be completed within a maximum of 12 months, included within the total period.

ABALA also offers to extend the guarantee of the works by 45 additional months to the year provided in the contract, bringing the total period to 57 months, equivalent to four years and nine months.

Recovery of maritime and salt heritage

The project will enable the spaces for the Museo del Mar y de la Sal, urbanise its surroundings, and rehabilitate the Casa de la Administración de las Salinas and the Caballete. The projects were drafted by Paredes Pedrosa Arquitectos, S.L. and were approved by the Junta de Gobierno Local (local government board) on 12 June 2026.

The regeneration of the Museo del Mar and its surroundings is part of the Plan de Actuación Integrado de Torrevieja and the Integrated Local Development Strategy, with co-financing from the European Union through the European Regional Development Fund (FEDER), within the framework of the Multi-Regional Programme of Spain 2021-2027.

After this agreement, the Mesa has submitted the proposal to the contracting authority to continue the steps prior to awarding the contract. It is planned to require ABALA to provide the documentation specified in the tender documents and to establish a definitive guarantee of €688,818.71, with a period of ten working days from the day after receipt of the request.